渗滤液处理站升级改造方案研究与工艺设计
杨超,金鑫,郭雨阁,金鹏康

Schematic studies and process design for reconstruction of a leachate treatment station
Chao YANG,Xin JIN,Yuge GUO,Pengkang JIN
表2 升级改造工艺效果
Table 2 Inlet and outlet water quality after reconstruction
项目CODBOD5NH4+-NTNTPSS色度
进水4 023.1±50.29864.2±23.16338.5±12.83402.1±19.9810±0.21732.8±34.95200±9.44
固液分离出水2 983.7±91.90603.1±9.23310.6±8.67395.1±11.185.2±0.26439.1±18.40164±3.97
水解酸化出水1 939.4±46.35781.2±15.40283.5±11.65302.4±13.885±0.08631.6±10.30281±10.82
MBR出水263.6±5.7762.1±0.7619.2±0.9331.3±0.850.5±0.011±0.0480±3.34
臭氧气浮出水153.1±2.0526.3±1.2818.8±0.5430.2±1.400.5±0.011±0.0120±0.37
DTRO出水56.7±1.1314.6±0.4816.4±0.6028.2±0.650.1±0.000.2±0.0110±0.12