Cause analyses and handling measures of the insufficient output in the desalination system by water treatment

Expand
  • 1. Henan Electric Power Research Institute, Zhengzhou 450052, China;
    2. Zhengzhou Heating Power Plant, Zhengzhou 450052, China

Received date: 2001-02-14

  Online published: 2010-10-01

Abstract

Aiming at the problems such as the large acid and alkali consumption, high self-using water ratio and seriously insufficient output in the first step desalination system of the Zhengzhou Heating Power Plant.Investigations have been made in situ.The main causes have been made analysed,handling measures have been presented and the problems have finally been solved.

Cite this article

WANG Fengtao, ZHANG Chunlei, ZHAO Zhanxing, WANG Ketao, LI Xianmin, ZHANG Li . Cause analyses and handling measures of the insufficient output in the desalination system by water treatment[J]. Industrial Water Treatment, 2001 , 21(8) : 40 -42 . DOI: 10.11894/1005-829x.2001.21(8).40

References

[1] 邵林.强碱性阴离子交换树脂的交换特性,水处理用离子交换树脂[M].北京:水利电力出版社,1989:229~235.
[2] 姚继贤,等.离子交换树脂的污染和复苏,工业锅炉水处理及水质分析[M].北京:中国劳动出版社,1993:187~195.