INDUSTRIAL WATER TREATMENT ›› 2005, Vol. 25 ›› Issue (3): 63-66. doi: 10.11894/1005-829x.2005.25(3).63

Previous Articles     Next Articles

Practice of the optimizing operation for KRC oil-braring wastewater treatment system

Li Ming1,2, 3   

  1. 1. China Geology University, Beijing 100083, China;
    2. China Petroleum and Natural Gas Huadong Prospect Design and Research Institute, Qingdao 266071, China;
    3. Xinjiang Kuerle Talimu Petrochemical Plant, Kuerle 841000, China
  • Received:2004-10-22 Online:2005-03-20 Published:2010-10-01

喀土穆炼油有限公司含油污水处理系统优化操作的实践

李明1,2, 李学军3   

  1. 1. 中国地质大学, 北京 100083;
    2. 中国石油天然气华东勘察设计研究院, 山东青岛 266071;
    3. 新疆库尔勒塔里木石化厂, 新疆库尔勒 841000
  • 作者简介:李明(1972- ),1995年毕业于陕西工学院电气自动化 专业,2001年毕业于北京航空航天大学MBA,院长助理, 高级工程师。现在中国地质大学(北京)攻读博士学位。电 话:0532-3892095.E-mail:Lixuejun@www.kvcsd.com。

Abstract:

The wastewater treatment plant has come into operation for four years,because the intake water caries frequently,analutical method has been limited and smooth operation of biochemical system couldn't be assured,the qualitu of outlet water is affected to a certain extent.Based on the data analusis coupled with practical operation,this article sums up the project of optimizing operation.It makes a foundation for the smooth operation of biochemical system and the assurence of ptoduct quality.

Key words: biochemical sysytem , sludge load , dissolved oxygen

摘要:

污水厂运行4年来,由于来水经常变化,监测分析方法有限,生化系统的平稳运行得不到保证,使出水质量受到一定影响。通过数据分析,结合实际操作,总结出优化操作方案,为生化系统的平稳运行和保证出水质量打下了基础。

关键词: 生化系统, 污泥负荷, 溶解氧