INDUSTRIAL WATER TREATMENT ›› 2011, Vol. 31 ›› Issue (4): 91-92. doi: 10.11894/1005-829x.2011.31.(4).91

Previous Articles    

Research on the prevention of low-temperature scaling in circulating water systems at oxygen producing factories and its application to water treatment techniques

Jiao Zhizeng1, Jin Xiuhong1, Guo Feng1, Wang Xiao1, Liu Zhanguo2   

  1. 1. CNOOC Tianjin Chemical Research & Design Institute, Tianjin 300131, China;
    2. Oxygen Factory, Chengde Zhaofeng Iron and Steel Group, Chengde 067600, China
  • Received:2010-12-28 Revised:2010-12-28 Online:2011-04-20 Published:2011-04-13

制氧循环水系统低温结垢研究及水处理技术应用

焦志增1, 金秀红1, 郭锋1, 王潇1, 刘占国2   

  1. 1. 中海油天津化工研究设计院, 天津300131;
    2. 承德兆丰钢铁集团制氧厂, 河北承德067600
  • 作者简介:焦志增(1979- ),2001 年毕业于河北工业大学,工程师。电话:022-26689320,E-mail:jiaozhizeng@yahoo.com.cn

Abstract:

Aiming at the problem of low-temperature scaling in circulating water systems at oxygen producing factories,suitable water treatment chemicals and water stabilizing technology have been used for avoiding the blocking phenomenon occurring to some critical equipments in pre-cooling systems at oxygen producing factories,such as air cooling towers and water cooling towers etc. The practice proves that the water treatment chemicals used and corresponding techniques have pretty good efficiencies in ensuring the long-term running with stability and safety for the circulating water systems at oxygen producing factories.

Key words: pre-cooling system, air cooling tower, water cooling tower, low-temperature scaling

摘要:

针对制氧厂循环水系统出现的低温结垢问题,采用合理的水处理药剂及水质稳定技术,避免制氧循环水系统中的空冷塔、水冷塔等预冷系统关键设备发生结垢堵塞现象,实践证明所用水处理药剂及相应水处理技术效果良好,可保障制氧循环水系统长周期安全稳定运行。

关键词: 预冷系统, 空冷塔, 水冷塔, 低温结垢