预臭氧+MBR+后臭氧工艺在焦化园区污水厂改造中的应用
Application of combined process pre ozone plus MBR and post ozone in sewage plant technical transformation project of coking park
收稿日期: 2023-03-17
Received: 2023-03-17
作者简介 About authors
李志雷(1984—),本科,高级工程师。电话:15318836228,E-mail:276277552@qq.com。
某焦化工业园污水处理厂因进水中总氰等有毒物质频繁超标、可生化性差等问题导致生化系统活性污泥培养困难,深度处理粉末活性炭消耗量过大,出水COD、TN等难以稳定达标。在原有工艺的基础上,将一级处理改造为臭氧预氧化+水解酸化池,破氰的同时提高了废水的可生化性;二级处理改造为A/A/O+MBR工艺,充分发挥生化处理工艺的脱氮除磷、降解有机物作用,MBR出水的低浊性也减少了后续臭氧的无效投加量;深度处理改造为臭氧氧化。2017年底改造完成后,此组合工艺展现出良好的运行效果,处理成本比改造前降低了3元/m3,出水COD、氨氮等主要指标稳定达到《地表水环境质量标准》(GB 3838—2002)Ⅴ类标准。
关键词:
Due to the frequent exceeding of toxic substances such as total cyanide in the inlet water,poor biochemical properties,etc,the sewage treatment plant of a coking industrial park had difficulties in the cultivation of activated sludge in the biochemical system,the large consumption of deeply treated powder activated carbon,and the COD and TN of the effluent difficult to stabilize. On the basis of the existing process,the primary treatment was transformed into ozone pre-oxidation and hydrolytic acidification tank,which improved the biodegradability of wastewater while breaking cyanide. The secondary treatment was transformed into A/A/O and MBR process,giving full play to the biochemical degradation of organic matter,nitrogen removal and phosphorus removal,and the low turbidity of MBR effluent reduced the ineffective amount of subsequent ozone. Advanced treatment was transformed into ozone oxidation. After the completion of the technical transformation at the end of 2017,this combination process showed a good operating effect,and the cost of post-technical transformation treatment was reduced by 3 yuan/m3 compared with that before the technical transformation. The main indicators such as effluent COD and ammonia nitrogen steadily reached the “Environmental Quality Standard for Surface Water”(GB 3838—2002) Class Ⅴ standard.
Keywords:
本文引用格式
李志雷, 刘宝富, 陈秀娟, 张德祥.
Zhilei LI, Baofu LIU, Xiujuan CHEN, Dexiang ZHANG.
山东省枣庄市某焦化园区污水处理厂设计规模为1万m3/d,原设计采用电解+气浮为预处理工段,(厌氧池+一沉池)(A/P)+(好氧池+二沉池)(O/P)为生化处理工段,活性炭粉池+砂滤池为深度处理工段。2016年初投产后,原工艺难以承受上游焦化企业排水中总氰等有毒物质的负荷冲击,低B/C造成活性污泥培养困难,生化池出水效果差,出水水质达标严重依赖深度处理工段投加粉末活性炭吸附,粉末活性炭消耗量大,危废处置成本很高。因此污水处理核心工艺改为“臭氧预氧化+水解酸化池+A/A/O生化池+MBR膜池+后臭氧氧化”的组合工艺,2017年底改造完成后运行效果良好,出水COD、氨氮等主要指标稳定达到《地表水环境质量标准》(GB 3838—2002)Ⅴ类标准。通过深入分析该厂改造前后的设计参数及运行情况等,可为同类焦化园区污水处理工程设计、运行及改造提供一定的参考。
1 改造前项目简介
1.1 进出水水质
表1 设计进出水水质
Table 1
水质指标 | 进水 | 出水 |
---|---|---|
pH | 6~9 | 6~9 |
悬浮物 | ≤70 | ≤10 |
COD | ≤300 | ≤40 |
氨氮 | ≤60 | ≤2 |
总氮 | ≤60 | ≤15 |
总磷 | ≤3.0 | ≤0.5 |
BOD5 | ≤100 | ≤10 |
1.2 改造前工艺流程
原设计采用电解+气浮为预处理工段,A/P+O/P为生化处理工段,炭粉池+砂滤池为深度处理工段,工艺流程如图1所示。
图1
1.3 改造前主要工段参数
(1)调节池。1座,尺寸L×B×H=40 m×25 m×5 m,有效容积4 500 m3,调节时间10.8 h。(2)电解槽。3套,2用1备,单台功率150 kW。水力停留时间0.5 h。(3)深层气浮池。2座,单座尺寸L×B×H=12 m×5 m×9 m。接触池上升流速10 mm/s,分离区向下流速1.5 mm/s。电解槽后污水100%加压进入溶气罐。(4)厌氧池。1座,L×B×H=39 m×24 m×8 m,停留时间15.3 h。(5)一沉池。1座,尺寸D×H=22 m×7 m,表面水力负荷1.1 m3/(m2·h)。(6)好氧池。1座,尺寸L×B×H=39 m×24 m×8 m,停留时间15.3 h。(7)二沉池。1座,尺寸D×H=22 m×7 m,表面水力负荷1.1 m3/(m2·h)。(8)活性炭粉池。1座,尺寸L×B×H=34.2 m×24.2 m×8 m,停留时间14.8 h。(9)三沉池。1座,尺寸D×H=22 m×7 m,表面水力负荷1.1 m3/(m2·h)。(10)砂滤池。2座,单座尺寸L×B×H=9.2 m×9.2 m×7 m,滤速2.5 m/h。(11)消毒池。1座,尺寸L×B×H=10 m×8 m×5 m,停留时间0.85 h。
1.4 改造前运行效果及存在的问题
1.4.1 运行效果
改造前污水处理量约9 000 t/d,各工艺段平均出水水质如表2所示。
表2 改造前各工艺段平均出水水质 (mg/L)
Table 2
水质 | COD | BOD5 | 氨氮 | 总氮 | 总磷 |
---|---|---|---|---|---|
调节池出水 | 280 | 32 | 48 | 54 | 2.12 |
气浮出水 | 266 | 30 | 46 | 52 | 1.26 |
厌氧池出水 | 240 | 35 | 44 | 50 | 1.13 |
好氧池出水 | 84 | 4.1 | 3.5 | 19 | 0.45 |
炭粉池出水 | 38 | 3.2 | 3.2 | 18 | 0.41 |
由表2可知,本次改造的重点指标是COD和总氮。改造前COD、氨氮等出水指标基本可以满足排放标准,但是生化段COD去除率较低,生化出水COD约80~90 mg/L,为保证总出水达标,活性炭粉池投加了大量的粉末活性炭。因为原生化池没有缺氧池,所以出水总氮超标。
1.4.2 改造前运行成本
改造前主要运行成本如表3所示。
表3 改造前主要运行成本
Table 3
费用名称 | 年使用量 | 年费用/万元 | 单位成本/(元·m-3) |
---|---|---|---|
合计 | 7.70 | ||
电耗 | 4 833 600 kW·h | 338.35 | 1.03 |
气浮用PAC溶液(10%) | 657 t | 32.85 | 0.10 |
PAM(阴离子) | 6.57 t | 10.51 | 0.03 |
次氯酸钠(10%) | 328.5 t | 32.85 | 0.10 |
乙酸钠(25%) | 394.2 t | 59.13 | 0.18 |
工资福利费 | 20人 | 120 | 0.37 |
粉末活性炭 | 547.5 t | 438 | 1.33 |
污泥危废处置费 | 2 918.18 t | 1 459.09 | 4.44 |
脱水用PAC溶液(10%) | 583.64 t | 29.18 | 0.09 |
脱水用PAM(阳离子) | 3.5 t | 9.45 | 0.03 |
自来水费 | 438 t | 0.15 | 0 |
1.4.3 存在问题及改造必要性
2 污水处理改造工艺论证
2.1 改造工艺路线
2.1.1 预处理工段改造路线
原设计电解槽存在使用困难、运行费用高的问题,所以此工段停运。原设计深层气浮池为全加压溶气气浮,为了降低运行费用,改造为部分回流加压溶气气浮,回流比为20%,溶气泵由2台55 kW降低为2台15 kW。为应对焦化废水特征污染物(氰类、酚类苯系物等)容易超标的情况,将现有厌氧池前段改造为臭氧预氧化池,臭氧对于含有氰化物或硫氰化物的废水有很好的处理效果;特别是对于硫氰化物,使用臭氧能够近乎100%将其去除〔3〕。在本项目改造后的实际运行过程中,投加20 mg/L的臭氧就可以将进水中5~6 mg/L的总氰降低到0.5 mg/L以下,对后续的生化过程无毒害作用。臭氧预氧化池在破氰的同时可使芳香烃、长链烷烃、杂环化合物等开环断链〔1〕,然后进入水解酸化池。根据产甲烷菌与水解产酸菌生长速度的不同,水解酸化池将厌氧处理控制在厌氧处理的前2个阶段,即在大量水解细菌、产酸菌作用下将不溶性有机物水解为溶解性有机物,将难生物降解的喹啉、萘、二联苯等大分子物质转化为易生物降解的有机酸、苯甲酸等小分子物质,从而提高焦化废水的可生化性。
2.1.2 生化处理工段改造路线
由表2可知,本次改造的主要目的是强化COD和总氮的去除。改造前生化出水COD为80~90 mg/L,出水总氮约20 mg/L。原好氧池尺寸L×B×H=39 m×24 m×8 m,总停留时间为15.3 h。为了强化脱氮除磷,将原好氧池改造为厌氧池+缺氧池+好氧池〔4〕,厌氧状态下,聚羟基丁酸酯(PHB)会在聚磷菌胞内积累,还会将胞内的聚磷裂解为单质磷并释放,然后在好氧池过量吸收磷,随着剩余污泥排放从而实现生物除磷;缺氧池是把上游来水、含有NO3--N的好氧池回流混合液利用反硝化菌进行反硝化反应,将废水中的NO3--N转化为N2,降低废水中的氮含量,同时降解部分COD;好氧池中利用充足的溶解氧和稳定的微生物菌群对有机物进行大幅度降解,硝酸菌和亚硝酸菌把废水中绝大部分的有机氮和NH3-N转化为NO3--N。因为膜分离能维持系统较高的污泥浓度,从而提高单位池容的处理负荷,并且实现较长的泥龄,使分解难降解有机物的菌种得以繁殖富集,因此将原活性炭粉池第1格改造为MBR膜池,组成AAO+MBR的生化单元。此工艺适于焦化废水的处理,对有机物、氨氮、总氮均有较好的去除效果。另外,膜组件的高效截留作用也可以保证膜出水的浊度很低,有利于后续的深度处理。
MBR膜池污泥回流入好氧池(回流比为400%),好氧池末端硝化液回流入缺氧池(回流比为300%),缺氧池后为厌氧池。缺氧池污泥质量浓度为6 000 mg/L,停留时间为5 h,单位MLSS脱氮负荷为0.04 kg/(kg·d)(以NO3--N计)。为保证脱氮效果,缺氧池前端按照碳氮比为3∶1的比例投加乙酸钠。厌氧池污泥质量浓度为6 000 mg/L,停留时间为1 h。好氧池污泥质量浓度为6 000 mg/L,停留时间为9.3 h,单位MLSS有机物负荷为0.08 kg/(kg·d)(以BOD5计)。如果不采用MBR工艺,单位MLSS缺氧池脱氮负荷将达0.06 kg/(kg·d)(以NO3--N计),好氧池单位MLSS有机负荷将达0.12 kg/(kg·d)(以BOD5计),冬季低温条件下硝化、反硝化效果会不稳定。
本项目改造后实际运行中,MBR膜池出水COD、氨氮、总氮等出水稳定,其中COD可以稳定到60 mg/L以下,比改造前降低了20 mg/L以上,较大地降低了深度处理费用。
2.1.3 深度处理工段改造路线
表4 臭氧氧化中试试验
Table 4
中试日期 | O3投加量/(mg·L-1) | 停留时间/h | 生化出水COD/(mg·L-1) | 臭氧出水COD/(mg·L-1) | COD去除率/% |
---|---|---|---|---|---|
2016-10-20 | 60 | 1.5 | 83 | 63.10 | 23.98 |
2016-10-20 | 60 | 2 | 83 | 61.55 | 25.84 |
2016-10-21 | 70 | 1.5 | 89 | 65.67 | 26.22 |
2016-10-21 | 70 | 2 | 89 | 64.00 | 28.09 |
2016-10-22 | 80 | 1.5 | 85 | 58.33 | 31.37 |
2016-10-22 | 80 | 2 | 85 | 56.43 | 33.61 |
2016-10-23 | 90 | 1.5 | 82 | 52.00 | 36.59 |
2016-10-23 | 90 | 2 | 82 | 49.10 | 40.12 |
2016-10-24 | 100 | 1.5 | 85 | 51.67 | 39.22 |
2016-10-24 | 100 | 2 | 85 | 49.29 | 42.02 |
2016-10-25 | 110 | 1.5 | 78 | 41.33 | 47.01 |
2016-10-25 | 110 | 2 | 78 | 38.71 | 50.37 |
2016-10-26 | 120 | 1.5 | 81 | 41.00 | 49.38 |
2016-10-26 | 120 | 2 | 81 | 38.14 | 52.91 |
2016-10-27 | 120 | 2.5 | 81 | 33.00 | 59.26 |
2016-10-28 | 120 | 2.5 | 80 | 32.10 | 59.88 |
2016-10-29 | 120 | 2.5 | 76 | 30.20 | 60.26 |
2016-10-30 | 120 | 2.5 | 87 | 39.31 | 54.82 |
2016-10-31 | 120 | 2.5 | 84 | 36.00 | 57.14 |
2016-11-1 | 120 | 2.5 | 79 | 31.54 | 60.08 |
由表4可知,臭氧氧化对本项目的COD有较好的去除效果,当臭氧投加量为120 mg/L,接触时间为2.5 h时,COD由约80 mg/L降低至40 mg/L以下,去除1 mg/L的COD需要约3 mg/L的O3。
对比了粉末活性炭吸附工艺和臭氧氧化工艺的运行成本,结果如表5所示。
表5 活性炭吸附与臭氧氧化运行成本对比
Table 5
工艺 | 费用名称 | 使用量 | 单价 | 单位成本/(元·m-3) |
---|---|---|---|---|
粉末活性炭吸附工艺(改造前) | 粉末活性炭 | 0.16 kg/t | 8元/kg | 3.38 |
污泥危废处置费 | 0.42 kg/t | 5元/kg | ||
臭氧氧化工艺(改造前) | 电耗 | 0.90 kW·h/t | 0.7元/(kW·h) | 1.83 |
液氧消耗量 | 1.20 kg/t | 1元/kg | ||
粉末活性炭吸附工艺(改造后) | 粉末活性炭 | 0.08 kg/t | 8元/kg | 1.69 |
污泥危废处置费 | 0.21kg/t | 5元/kg | ||
臭氧氧化工艺(改造后) | 电耗 | 0.90 kW·h/t | 0.7元/(kW·h) | 0.92 |
液氧消耗量 | 1.20 kg/t | 1元/kg |
2.2 改造工艺路线确定
根据以上分析,确定改造后的工艺流程如图2所示。
图2
3 改造工艺设计
3.1 改造工艺单元设计
(1)气浮池。全加压溶气气浮池改造为部分回流加压溶气气浮沉淀池,具体参数:2座,接触池上升流速10 mm/s,分离区向下流速1.5 mm/s,溶气水回流比20%。溶气水回流泵3台,2用1备,单台水泵参数:Q=42 m3/h,H=60 m,N=15 kW。
(2)臭氧预氧化池+水解酸化池。现有厌氧池+一沉池改造为臭氧预氧化池+缓冲池+水解酸化池+一沉池,具体参数:臭氧预氧化池,1座,整体加混凝土现浇盖封闭,顶部设置正负压呼吸阀和尾气破坏器。臭氧接触时间1.5 h,臭氧投加量20 mg/L;缓冲池,1座,缓冲时间1 h;水解酸化池,1座,停留时间12.5 h。
(3)A/A/O生化池。原好氧池改造为A/A/O生化池,设计污泥质量浓度6 000 mg/L,从前往后依次为:缺氧池,1座,停留时间5 h;厌氧池,1座,停留时间1 h;好氧池,1座,停留时间9.3 h。
(4)MBR膜池+后臭氧接触池。现有活性炭粉池共3格,其中第1格改造为MBR膜池,第2格改造为后臭氧接触池,第3格保留为活性炭粉池,作为后保险措施。
(5)MBR膜池。设计1座4格。中间设配水渠,1配4,均匀将进水配入4格膜池。单格膜池,配置7个膜架,膜通量9.8 L/(m2·h)。PVDF材质,孔径<0.1 μm。配置清洗系统,包括在线清洗和离线清洗。在线清洗采用9+1的模式,即过滤9 min,停止运行反冲洗1 min。膜池4格,离线清洗时放空1格,另外3格承担全部流量,膜通量临时增加至13 L/(m2·h)。待离线清洗的膜池放空后,先碱洗然后再酸洗,碱性清洗药剂为有效氯质量浓度2 000~3 000 mg/L、pH 10~11的NaClO溶液,酸性清洗药剂为0.2%盐酸,浸泡时间:碱洗6~24 h、酸洗2 h。进水、排泥电动闸门各4台。
(6)膜设备间。MBR膜池旁边新建膜设备间,采用轻钢结构,层高H=4.9 m。主要设备配置如下:产水泵4台,设备参数:Q=105 m3/h,H=10 m,N=5.5 kW。另外配置混合液回流泵2台,真空泵1套,反洗水泵1台,空压系统1套,反冲鼓风机2台。
(7)后臭氧接触池。1座,整体加混凝土现浇盖封闭,顶部设置正负压呼吸阀和尾气破坏器。臭氧接触时间2.5 h,臭氧投加量80~120 mg/L。
3.2 改造投资
本项目改造总投资2 124.99万元,其中直接费用1 604.11万元,间接费用520.88万元。直接费用中建筑工程费用260.59万元,设备购置费1 125.80万元,安装工程费用217.72万元。
3.3 主要运行成本
改造后主要运行成本如表6所示。
表6 改造后主要运行成本
Table 6
费用名称 | 数值 | 单价/元 | 年费用/万元 | 单位成本/(元·m-3) |
---|---|---|---|---|
合计 | 4.73 | |||
电耗 | 0.7 kW·h/a | 4 927 500 | 344.93 | 1.05 |
气浮用PAC溶液(10%) | 657 t/a | 500 | 32.85 | 0.10 |
PAM(阴离子) | 6.57 t/a | 16 000 | 10.51 | 0.03 |
次氯酸钠(10%) | 328.5 t/a | 1 000 | 32.85 | 0.10 |
乙酸钠(25%) | 394.2 t/a | 1500 | 59.13 | 0.18 |
工资福利费 | 20人 | 60 000 | 120 | 0.37 |
污泥处置费(危废) | 636.93 t/a | 5 000 | 318.46 | 0.97 |
污泥处置费(一般固废) | 912.5 t/a | 200 | 18.25 | 0.06 |
脱水用PAC溶液(10%) | 309.89 t/a | 500 | 15.49 | 0.05 |
脱水用PAM(阳离子) | 1.86 t/a | 27 000 | 5.02 | 0.02 |
液氧 | 2 920 t/a | 1 000 | 292 | 0.89 |
自来水费 | 438 t/a | 3.5 | 0.15 | 0.000 5 |
MBR膜更换费用 | 10 640 m2/a | 120 | 127.68 | 0.39 |
改造新增折旧费 | 0.29 | |||
改造新增维修费 | 0.25 |
4 实际运行效果及跟踪研究
4.1 实际运行效果
本项目于2017年年底运行至今,运行效果良好,出水稳定达标,处理量约9 000 m3/d以上。2021年—2022年逐月平均实测进出水水质如表7所示。
表7 2021—2022年月平均进出水水质 (mg/L)
Table 7
日期 | 项目 | COD | 氨氮 | 总氮 | 总磷 |
---|---|---|---|---|---|
2021年5月 | 总进水 | 290 | 48 | 55 | 2.1 |
总出水 | 32 | 0.9 | 12.1 | 0.42 | |
2021年6月 | 总进水 | 286 | 49 | 54 | 1.8 |
总出水 | 28 | 0.8 | 11.3 | 0.35 | |
2021年7月 | 总进水 | 279 | 51 | 56 | 1.7 |
总出水 | 34 | 1.2 | 13.4 | 0.36 | |
2021年8月 | 总进水 | 288 | 45 | 53 | 2.2 |
总出水 | 36 | 0.6 | 13.6 | 0.39 | |
2021年9月 | 总进水 | 269 | 44 | 49 | 1.6 |
总出水 | 27 | 0.5 | 11.8 | 0.33 | |
2021年10月 | 总进水 | 282 | 46 | 52 | 1.7 |
总出水 | 29 | 0.6 | 12.2 | 0.35 | |
2021年11月 | 总进水 | 287 | 47 | 54 | 2.2 |
总出水 | 31 | 0.9 | 12.9 | 0.41 | |
2021年12月 | 总进水 | 276 | 46 | 55 | 2.6 |
总出水 | 36.8 | 1.84 | 13.8 | 0.46 | |
2022年1月 | 总进水 | 260 | 43 | 48 | 1.9 |
总出水 | 33 | 1.4 | 12.5 | 0.42 | |
2022年2月 | 总进水 | 286 | 48 | 52 | 2.1 |
总出水 | 34 | 0.9 | 13.4 | 0.37 | |
2022年3月 | 总进水 | 274 | 50 | 55 | 1.9 |
总出水 | 35 | 0.8 | 14.1 | 0.39 | |
2022年4月 | 总进水 | 279 | 43 | 51 | 2.2 |
总出水 | 34 | 1.1 | 13.8 | 0.37 | |
平均值 | 总进水 | 279.7 | 46.7 | 52.8 | 2.0 |
总出水 | 32.5 | 0.96 | 12.9 | 0.385 |
由表7可知,本项目改造后运行效果良好,总出水可以稳定达到设计标准。
4.2 跟踪研究
(1)本项目改造后采用了前后臭氧氧化工艺,在臭氧接触池的尾气破坏器后,大量的纯氧直接排放。后续增加了臭氧尾气增压系统和纯氧曝气机,对臭氧尾气利用进行了很好的尝试,实际可节省约20%的鼓风机能耗。
(2)本项目改造设计了2台20 kg/h的液氧源型臭氧发生器,原设计采用处理后中水作为冷却水源,但是实际运行中发现在夏季时处理后的中水温度较高,冷却效果不佳,影响臭氧发生器效率,因此增加了2台100 t/h的循环冷却塔,循环冷却效果良好。
(3)本项目原设计了2套板框脱水机,并联运行。实际运行中,气浮污泥被认定为危险废物,生化污泥被认定为一般固废,处置方向及处置成本明显不同。因此后续将浓缩池和板框脱水机改造为2套独立的系统(1套处理气浮污泥、1套处理生化污泥),大大降低了污泥的处置费用。
5 结论
(1)本项目验证了预臭氧氧化+水解酸化+A/A/O生化池+MBR工艺+后臭氧氧化的组合工艺对焦化工业园污水处理的适用性,从2017年年底运行至今,本项目运行灵活、可靠,运行成本较改造前降低约3元/t,对于同类型焦化工业园污水处理的设计、改造等具有一定的示范性。
(2)本项目改造充分利用原有构筑物,厌氧池改造为预臭氧池+缓冲池+水解酸化池,好氧池改造为AAO生化池,活性炭粉池改造为MBR膜池+后臭氧氧化池+活性炭粉池,对于同类型的改造项目具有一定的参考性。
参考文献
焦化废水深度处理技术综述
[J].
Summary on the advanced treatment technology of coking wastewater
[J].
焦化废水处理工程设计实例及运行效果
[J].
Case study on design and operation of a coking wastewater treatment project
[J].
不同药剂化学氧化预处理焦化废水的比选
[J].
Comparison of the chemical oxidation pretreatment of coking wastewater by using different agents
[J].
物化-生化组合工艺处理焦化废水的工程实例
[J].
Case study on the physicochemical-biochemical process for the treatment of coking wastewater
[J].
臭氧深度处理焦化废水尾水及臭氧尾气利用研究
[J].
Researches on the advanced treatment of coking wastewater tail water and the utilization of ozone tail gas
[J].
/
〈 |
|
〉 |
