There are many kinds of pollutants (pH 2 ~ 3, containing floride 60 mg/L,total phosphorous 40 mg/L, NH3 - N 40 mg/L and SS 130 mg/L, etc) in acidic the phosphoric amine-containg wastewater. The requirements of the treated effluent are as follows: F 10 mg/L,TP 0.5 mg/L, NH3 - N 15 mg/L,pH 6 ~ 9. On the basis of the features of the wastewater, lime hydrolytic acidification is firstly adopted in order to remove NH3 - N and phosphorus. Then flocculation and flotation is used to treat SS and part of COD. Finally activated-Al2O3 is added to the wastewater, to absorb most of the remained pollutants. The quality of effluent is conform to the requirements. Through economic analysis of its investment, the total cost is about 4.831 million yuan, it takes 0.67 yuan/m3 on the wastewater treatment. We can draw such a conclusion that the design is feasible and economically reasonable.
Key words:
phosphoric amine-containing wastewater,
acidification-hydrolysis,
flocculation and flotation adsorption
摘要:
某磷胺废水呈酸性(pH2~3),含氟化物60mg/L,总磷40mg/L,氨氮约40mg/L,SS约130mg/L,综合处理后的出水要求为氟化物<10mg/L,总磷<0.5mg/L。设计针对该废水特性,先采用石灰水解酸化,去除NH3-N和P,接着采用絮凝与气浮去除悬浮物和部分的COD,最后采用活性Al2O3吸附水中残留物,出水可望达标。技术经济分析,投资总费用为483.1万元,按流量150m3/h,处理成本为0.67元/m3,设计工艺可靠且经济合理。
关键词:
磷胺废水,
酸化水解,
絮凝浮选吸附
CLC Number:
Zeng Jing, Peng Qinglin, Guo Xianghong. Study on the technological design of phosphoric amine-containing wastewater treatment[J]. INDUSTRIAL WATER TREATMENT, 2004, 24(2): 64-67.
曾经, 彭青林, 郭湘洪. 磷胺废水处理工艺的设计初探[J]. 工业水处理, 2004, 24(2): 64-67.